Create the construction access, service routes and working areas that allow the port and industrial packages to progress together. This phase provides the practical foundation for daily execution: safe circulation, clear work fronts, survey control, construction services and space for materials and equipment. The permanent road and utility layout guides the temporary arrangements so early work supports the completed campus. Interfaces with the pharmaceutical and banking programmes remain coordinated through the programme office, while marine construction and industrial building teams receive defined access and service connections.
Scope of delivery
Establish construction entrances, internal haul routes, work areas and controlled pedestrian access for the first delivery packages.
Prepare site levels, drainage routes, ground-treatment zones and service crossings in the released construction areas.
Install the temporary water, power, communications and site facilities required by survey, civil and marine teams.
Reserve permanent utility corridors, freight routes and equipment-access envelopes within the enabling-work layout.
What this phase hands over
Usable construction access and working areas connected to the programme’s marine and landside work fronts.
A coordinated plan of site levels, drainage, crossings and service reservations for subsequent construction.
Temporary services and site facilities sized to the active teams, plant and construction activities.
Handover records identifying completed enabling areas, access conditions and interfaces to the following packages.
Additional construction view · Milestone 03
The work behind the investment.
Site access and enabling infrastructure. This large construction view develops the work package within the expanded harbour and AVIS industrial-park masterplan.
Milestone 03 · Site access and enabling infrastructure · AVIS construction development
Construction payment 03 · 4%€100,000,000
AVIS-TN-03 Main construction investment including the harbour
Place laydown areas and temporary facilities with the final operating layout in view. Some areas can become maintenance yards or logistics spaces after construction. Others must be cleared in sequence so the permanent road, rail and building packages can proceed without avoidable relocation.
Utilities before congestion
Coordinate below-ground services early, including water, drainage, electrical ducts and communications. Map crossing points and maintenance access before roads, crane routes and industrial foundations make later installation more difficult. Each service corridor should connect clearly to the packages that depend on it.
Release work fronts progressively
Divide enabling works into defined areas with clear boundaries and handover records. Marine contractors, building teams and industrial installers can then plan against the areas available to them. Track access and utility interfaces through the same programme register used for design and equipment delivery.
Execution logistics
Connect the work.
Sequence heavy deliveries around the prepared haul routes and lifting areas. Separate bulk materials, structural components and sensitive equipment storage. Keep construction traffic connected to designated entrances and allow industrial equipment to reach future installation locations without crossing completed operational areas unnecessarily.
Delivery interfaces
Milestone & handover
Enabling milestone: prepared work fronts, access and construction services are handed to the next delivery teams.
The masterplan and released engineering layouts define access, levels, corridors and working-area boundaries.